A 4 in thick 8x10 slab needs 47 bags of 80 lb concrete.

That is 26.7 cubic feet (0.99 cubic yards), including 5% waste. In other bag sizes: 63 × 60 lb, or 94 × 40 lb.

Bags are the right call here. At 0.99 cubic yards you are under the point where ready-mix delivery makes sense, and most suppliers have a minimum load plus a short-load fee. 47 bags is a manageable day with a wheelbarrow or a small mixer.

Where that number comes from

  1. 8 ft × 10 ft = 80 sq ft
  2. 4 in thick = 0.3333 ft, so 80 × 0.3333 = 26.7 cubic feet
  3. An 80 lb bag yields 0.6 cu ft, so 26.7 ÷ 0.6 = 45 bags
  4. Add 5% for spillage and uneven subgrade = 47 bags

Bag yields are the finished volume of mixed concrete, not the dry weight, and they differ by brand by a few percent. The 5% margin absorbs that along with the low spots every real excavation has.

Change the numbers

What goes under the slab

  • Compacted gravel base, 4 in: about 0.99 cubic yards for this slab.
  • Rebar: #3 or #4 on an 18 in grid for a slab this size, kept up off the ground on chairs so it sits in the middle of the pour, not at the bottom.
  • Control joints: cut them at roughly 2.5 times the slab thickness in feet — about every 10.0 ft at 4 in. Concrete cracks; joints decide where.

Getting it right

  • Forgetting the base. Concrete poured onto soft ground will crack no matter how many bags you buy. Compacted gravel first.
  • Sizing off nominal thickness. Forms settle and subgrade dips. A slab "4 inches thick" usually consumes 5-10% more than the arithmetic says.
  • Mixing too wet. Extra water makes it easier to place and markedly weaker. Follow the water on the bag.
  • Running out mid-pour. A cold joint between yesterday's concrete and today's is a permanent weak line. Have every bag on site before you start.